Construction Update - 10/6/2021 Magnolia-Dearborn

Elm-Intersectio_20211006-191535_1

Wright Construction has been placing the paver bricks in the intersection of Elm/Magnolia and Dearborn Street and anticipates finishing that intersection by October 15. Possibly by October 13, weather permitting at which time they will be closing Orange Street intersection. The pervious concrete parking spaces in front of Englewood's On Dearborn and StyleCraft Cabinetry and Construction have been poured. The concrete for the new paver brick sidewalks has been poured and they are placing bricks along the north side of the street between Elm and Orange Street.

With the opening of the Elm/Magnolia intersection, demolition of the Orange Street intersection will begin. Wright Construction will also be demolishing the sidewalks and driveways on the southside of Dearborn, between Elm and Orange and the sidewalk on the north side of Dearborn between Orange and Mango. This work will happen between October 18 - 22. The construction of the new driveways and the paver brick sidewalks will immediately follow demolition.
Englewood CRA Newsletter, 10/6/2021

Englewood's on Dearborn's side walk is completed, and the replacement parking spaces are drying.

Artists Rendition of sample proposed final intersection. 


B2ap3 Thumbnail 242036984 411008997032724 2237032869679283234 N

Construction Update - 9/15/2021 Magnolia-Dearborn

The intersection of Dearborn St and Elm/Magnolia Avenues are still under construction but moving right along. The sand base for the slab before the pavers is laid, and the curbs and sidewalk sections are being laid. Debbie Marks today stated...
https://englewoodfl.org/news-blog/construction-update-9-15-2021-magnolia-dearborn-1
B2ap3 Thumbnail 20210824DearbornMagnolia 2

W. Dearborn Street Improvement Project

On Tuesday, August 24, work officially started at the intersection of Elm/Magnolia and W. Dearborn Street. Demolition work is underway. At the same time, the sidewalk and parking on the north side of the block between Elm and Orange is being removed to make way for the new pavers and pervious parking spaces. The memorial bricks are being gathered a...
https://englewoodfl.org/news-blog/w-dearborn-street-improvement-project
B2ap3 Thumbnail DetourConceptMap Thumb Large800 0

Construction Update - 8/19/2021 Magnolia-Dearborn

Construction Update Construction will begin on Tuesday, August 24 with the closing of the intersection of Elm/Magnolia and W. Dearborn Street. Re-construction of that intersection will take approximately 30 days (depending on weather). 
https://englewoodfl.org/news-blog/construction-update-001-8-19-2021-magnolia-dearborn
Englewood Farmer's Market opened Today. Welcome Ba...
25th Annual Halloween Safe Walk
 

Comments

Already Registered? Login Here
No comments made yet. Be the first to submit a comment

By accepting you will be accessing a service provided by a third-party external to https://oldenglewood.com/

No Internet Connection